Page   

TABLE OF CONTENTS                                                                                                                                                            Page

 

Executive SUMMARY

 

1.0

INTRODUCTION

1

 

 

 

2.0

PROJECT INFORMATION

 

 

2.1 Background

1

 

2.2 Site Description

2

 

2.3 Construction Programme

2

 

2.4 Project Organization and Management Structure Milestones of Environmental Protection / Mitigation activities annotated

2

 

2.5 Contact Details of Key Personnel

 

 

 

 

3.0

Construction Progress in this quarter

2

 

 

 

4.0

Air Quality Monitoring

 

 

4.1 Monitoring Requirement

3

 

4.2 Monitoring Parameters, Frequency and Duration

3

 

4.3 Action and Limit Levels

3

 

4.4 Event-Action Plans

5 – 3

 

4.5 Results

3

 

 

 

5.0

Impact Noise Monitoring

 

 

5.1 Monitoring Requirements

4

 

5.2 Monitoring Parameters, Frequency and Duration

6 – 476

 

5.3 Action and Limit Levels

4

 

5.4 Event-Action Plans

48

 

5.5 Results

4 – 5 – 9

 

 

 

6.0

Water quality monitoring

59

 

 

 

7.0

environmental Non-conformance

 

 

7.1 Summary of air quality, noise and water quality monitoring

59

 

7.2 Summary of Environmental Complaints

5

 

7.3 Summary of Notification of Summons and Prosecution

5

 

 

 

8.0

Site Inspection

5

 

8.1 Summary of the site inspection findings and Action(s) taken by KLKJV and ET

5 – 100

 

8.2 Status of Environmental Licensing and Permitting

100

 

 

 

9.0

Waste Management

 

 

9.1 Waste Management Audit

111

 

9.2 Records of Waste Quantities

111

 

 

 

10.0

Implementation Status

 

 

10.1 Implementation Status of Environmental Mitigation Measures

111 – 12

 

10.2 Implementation Status of Event and Action Plan

122

 

10.3 Implementation Status of Environmental Complaint Handling

122

 

10.4 Implementation Status of Notification of Summons and Prosecution

12

 

 

 

11.0

Conclusion, comments and recommendations

2

 

11.1 Conclusions

13

 

11.2 Comments and Recommendations

13 – 14

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

APPENDIX

 

A

Organization Chart and Lines of Communication

 

B

Graphical Plots of Impact Air Quality Monitoring Data

 

C

Graphical Plots of Impact Noise Monitoring Data

 

D

Data of Weather Station

 

E

Event-Action Plans

 

F

Construction Programme

 

G

Summary of Implementation Status of Mitigation Measures in this quarter

 

 

 

 

 

 

 

Figures

 

Drawing No. 23400/EN/098

Ngong Ping Sewage Project Scheme – General Layout

Drawing No. 23400/T/069

Portion of Site and Works Area (Sheet 1 to Sheet 9)

Drawing No. 23400/R/004

Air & Noise Sensitive Receivers around Ngong Ping Area

Drawing No. 23400/EN/094

Locations of Noise and Dust Monitoring Stations

 

 

 

 

Tables

 

2.1

Contact Details of Key Personnel

4.1

Monitoring parameters, duration and frequency of impact air quality monitoring

4.2

Action and Limit Levels for 24-hr TSP and 1-hr TSP (Please include the date of monitoring in the x-axis of the charts)

5.1

Duration, Frequencies and Parameters of Noise Monitoring

5.2

Action and Limit levels for noise monitoring

8.1

The summary of the site inspection findings and Action(s) taken by KLKJV and ET

8.2

Summary of Environmental Licensing and Permit Status

9.1

Summary of Quantities of Waste for Disposal in this quarter

10.1

Statistical Summary of Environmental Complaints