Page
TABLE OF CONTENTS
|
1.0 |
1 |
|
|
|
|
|
|
2.0 |
|
|
|
|
2.1 Background |
1 |
|
|
2.2 Site Description |
2 |
|
|
2.3 Construction
Programme |
2 |
|
|
2.4 Milestones of
Environmental Protection / Mitigation activities annotated |
2 |
|
|
|
|
|
3.0 |
2 |
|
|
|
|
|
|
4.0 |
|
|
|
|
4.1 Monitoring
Requirement |
2 – 3 |
|
|
4.2 Monitoring
Equipment |
3 |
|
|
4.3 Monitoring
Parameters, Frequency and Duration |
3 |
|
|
4.4 Monitoring
Locations and Schedule |
3 – 4 |
|
|
4.5 Monitoring
Methodology |
4 – 5 |
|
|
4.6 Action and Limit
Levels |
5 |
|
|
4.7 Event-Action
Plans |
6 |
|
|
4.8 Results |
6 |
|
|
|
|
|
5.0 |
|
|
|
|
5.1 Monitoring
Requirements |
6 |
|
|
5.2 Monitoring
Equipment |
6 |
|
|
5.3 Monitoring
Parameters, Frequency and Duration |
6 – 7 |
|
|
5.4 Monitoring
Locations and Period |
7 |
|
|
5.5 Monitoring Methodology |
7 – 8 |
|
|
5.6 Action and Limit
Levels |
8 |
|
|
5.7 Event-Action
Plans |
8 |
|
|
5.8 Results |
8 – 9 |
|
|
|
|
|
6.0 |
9 |
|
|
|
|
|
|
7.0 |
|
|
|
|
7.1 Summary of air
quality, noise and water quality monitoring |
9 |
|
|
7.2 Summary of
Environmental Complaints |
9 |
|
|
7.3 Summary of
Notification of Summons and Prosecution |
9 |
|
|
|
|
|
8.0 |
9 |
|
|
|
8.1 Summary of the
site inspection findings and Action(s) taken by KLKJV and ET |
9 – 10 |
|
|
8.2 Status of
Environmental Licensing and Permitting |
10 |
|
|
8.3 Recommendations
on site inspection findings in Site Inspections of this month |
10 –11 |
|
|
|
|
|
9.0 |
|
|
|
|
9.1 Waste Management
Audit |
11 |
|
|
9.2 Records of Waste
Quantities |
11 |
|
|
|
|
|
10.0 |
|
|
|
|
10.1 Implementation
Status of Environmental Mitigation Measures |
11 – 12 |
|
|
10.2 Implementation
Status of Event and Action Plan |
12 |
|
|
10.3 Implementation
Status of Environmental Complaint Handling |
12 |
|
|
|
|
|
11.0 |
12 |
|
|
|
|
|
|
12.0 |
|
|
|
|
12.1 Upcoming
EM&A Schedule in coming two months |
12 |
|
|
12.2 Upcoming
construction works schedule in the coming months |
13 |
|
|
|
|
|
|
|
|
|
APPENDIX |
|
|
|
A |
|
|
|
B1 |
Calibration
Certificates for Impact Air Quality Monitoring Equipment |
|
|
B2 |
|
|
|
B3 |
|
|
|
C1 |
Calibration Certificates for Impact Noise
Monitoring Equipment |
|
|
C2 |
|
|
|
C3 |
|
|
|
D |
|
|
|
E |
|
|
|
F |
|
|
|
G |
Summary
of Implementation Status of Mitigation Measures during Site Inspection |
|
|
Figures |
|
|
Ngong Ping Sewage
Project Scheme – General Layout |
|
|
Portion of Site and
Works Area (Sheet 1 to Sheet 9) |
|
|
Air & Noise
Sensitive Receivers around Ngong Ping Area |
|
|
Locations of Noise
and Dust Monitoring Stations |
|
|
|
|
|
Tables |
|
|
2.1 |
Contact Details of
Key Personnel |
|
4.1 |
Air Quality
Monitoring Equipment |
|
4.2 |
Monitoring
parameters, duration and frequency of impact air quality monitoring |
|
4.3 |
Air Quality
Monitoring Locations |
|
4.4 |
Monitoring Schedule
for air quality monitoring stations |
|
4.5 |
Action and Limit
Levels for 24-hr TSP and 1-hr TSP |
|
5.1 |
Noise Monitoring
Equipment |
|
5.2 |
Duration,
Frequencies and Parameters of Noise Monitoring |
|
5.3 |
Noise Monitoring
Locations |
|
5.4 |
Monitoring Periods
for noise monitoring stations |
|
5.5 |
Action and Limit
levels for noise monitoring |
|
8.1 |
The summary of the
site inspection findings and Action(s) taken by KLKJV and ET |
|
8.2 |
Summary of Environmental
Licensing and Permit Status |
|
9.1 |
Summary of
Quantities of Waste for Disposal in this reporting month |
|
10.1 |
Statistical Summary
of Environmental Complaints |
|
12.1 |
Upcoming EM&A
Schedule in coming two months |
|
12.2 |
Construction Plan in
the coming months |