TABLE OF CONTENTS                                                                                                                   Page

                                                                                                                                                                                                                                                                                                                       

Executive SUMMARY

1.0

INTRODUCTION

1

 

 

 

2.0

PROJECT INFORMATION

1

 

2.1 Background

1

 

2.2 Project Location and Scope

1

 

2.3 Construction Programme

1

 

2.4 Project Organization and Management Structure

2

 

2.5 Contact Details of Key Personnel

2

 

 

 

3.0

construction progress in this reporting month

2

 

 

 

4.0

Marine water quality monitoring

 

 

4.1 Monitoring Locations

2 – 3

 

4.2 Monitoring Parameters

3

 

4.3 Monitoring Frequency

3

 

4.4 Monitoring Methodology and Equipment Used

3 – 4

 

4.5 Quality Assurance (QA) / Quality Control (QC) results and Determination Limits

4 – 5

 

4.6 Details of site Equipment used for In-situ measurement

5

 

4.7 Action and Limit Level

5

 

4.8 Event-Action Plans

5

 

4.9 Monitoring Duration and Period

6

 

4.10 Marine Water Monitoring Results

6

 

 

 

5.0

Ecology Monitoring

 

 

5.1 Introduction

7

 

5.2 Monitoring Procedure

7

 

5.3 Monitoring Frequency and Schedule

7

 

5.4 Result and Observation

7

 

 

 

6.0

Environmental Non-conformance

 

 

6.1 Summary of environmental monitoring

7

 

6.2 Summary of environmental complaints

7

 

6.3 Summary of notification of summons and prosecutions

7

 

 

 

7.0

Waste Management

 

 

7.1 Waste Management Audit

7

 

7.2 Records of Waste Quantities

8

 

 

 

8.0

Environmental audit

 

 

8.1 Site Inspection

8

 

8.2 Status of Environmental Licensing and Permitting

8

 

8.3 Implementation Status of Environmental Mitigation Measures

8 – 9

 

8.4 Recommendations on site inspection findings

9

 

8.5 Implementation Status of Event and Action Plan

9

 

8.6 Implementation Status of Environmental Complaint Handling

9

 

8.7 Implementation of Notification of Summons and Prosecution

9

 

 

 

9.0

Conclusion

9

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

APPENDIX

 

A

Organization Chart

 

B1

Calibration Certificates of Impact Monitoring Equipments

 

B2

Impact Monitoring Results

 

C

Graphical Plots of Impact Monitoring Data

 

D

Weather Condition during Impact Monitoring

 

E

Construction Programme of the Project

 

F

Event-Action Plans

 

G

QA/QC Results of Laboratory Analysis

 

H

Summary of Implementation Status of Mitigation Measures

 

 

 

 

 

 

 

 

 

 

 

 

 

Figure

 

Figure 1

Construction of Lung Kwu Chau Jetty

TS-2031

Proposed Marine Water Quality Monitoring Stations

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page

Tables

 

2.1

Contact Details of Key Personnel

2

3.1

Implementation of Environmental Mitigation Measures

2

4.1

Marine Water Quality Monitoring Stations

3

 

4.2

Monitoring Parameters

3

 

4.3

Other relevant water quality parameters

3

 

4.4

Monitoring Frequency of Impact Monitoring

3

 

4.5

The Summary of laboratory testing method of total suspended solids

5

 

4.6

Details of Impact Monitoring Equipment (In-situ measurement)

5

 

4.7

Water Quality Action and Limit Levels

5

 

4.8

Time Schedule of Water Quality Monitoring at Lung Kwu Chau

6

 

4.9

Summary of Marine Water Quality Exceedances in this reporting month

6

 

4.10

Daily Exceedance summary of marine water quality

6

 

7.1

Summary of Quantities of Waste for Disposal in this reporting month

8

8.1

Summary of environmental licensing and permit status

8