CONSTRUCTION OF JETTY AT LUNG KWU CHAU

(CED CONTRACT NO.: CV/2002/11)

FIRST MONTHLY EM&A REPORT

(9 JUNE TO 8 JULY 2003)

 

View Full-Sized Picture

View Full-Sized Picture

 

TABLE OF CONTENTS
Executive Summary
1 INTRODUCTION
2 PROJECT INFORMATION
2.1 Background
2.2 Project Location and Scope
2.3 Construction Programme
2.4 Project Organization and Management Structure
2.5 Contact Details of Key Personnel
3 CONSTRUCTION PROGRAMME IN THIS REPORTING MONTH
4 MARINE WATER QUALITY MONITORING
4.1 Monitoring Locations
4.2 Monitoring Parameters
4.3 Monitoring Frequency
4.4 Monitoring Methodology and Equipment Used
4.5 Quality Assurance (QA) / Quality Control (QC) results and Determination Limits
4.6 Details of site Equipment used for In-situ measurement
4.7 Action and Limit Level
4.8 Event-Action Plans
4.9 Monitoring Duration and Period
4.10 Marine Water Monitoring Results
4.11 Explanation of Exceedances
5 ECOLOGY MONITORING
5.1 Introduction
5.2 Monitoring Procedure
5.3 Monitoring Frequency and Schedule
5.4 Result and Observation
6 WASTE MANAGEMENT
6.1 Waste Management Audit
6.2 Records of Waste Quantities
6.3 Summary of dredging volume in this reporting month
7 ENVIRONMENTAL AUDIT
7.1 Site Inspection
7.2 Status of Environmental Licensing and Permitting
7.3 Implementation Status of Environmental Mitigation Measures
7.4 Recommendations on site inspection findings
7.5 Implementation Status of Event and Action Plan
7.6 Implementation Status of Environmental Complaint Handling
7.7 Implementation of Notification of Summons and Prosecution
8 CONCLUSION
9 FUTURE KEY ISSUE
9.1 Upcoming EM&A Schedule
9.2 Upcoming construction works schedule in coming two month
APPENDIX
A Organization Chart
B1 Calibration Certificates of Impact Monitoring Equipments
B2 Impact Monitoring Results
C Graphical Plots of Impact Monitoring Data
D Weather Condition during Impact Monitoring
E Construction Programme of the Project
F Event-Action Plans
G QA/QC Results of Laboratory Analysis
H Summary of Implementation Status of Mitigation Measures
Figure
Figure 1 Construction of Lung Kwu Chau Jetty
TS-2031 Proposed Marine Water Quality Monitoring Stations
Photos
Photo 1 to Photo 10
Tables
2.1 Contact Details of Key Personnel
3.1 Implementation of Environmental Mitigation Measures
4.1 Marine Water Quality Monitoring Stations
4.2 Monitoring Parameters
4.3 Other relevant water quality parameters
4.4 Monitoring Frequency of Impact Monitoring
4.5 The Summary of laboratory testing method of total suspended solids
4.6 Details of Impact Monitoring Equipment (In-situ measurement)
4.7 Water Quality Action and Limit Levels
4.8 Time Schedule of Water Quality Monitoring at Lung Kwu Chau
4.9 Summary of Marine Water Quality Exceedances in this reporting month
4.10 Daily summary of record of marine water quality
6.1 Summary of Quantities of Waste for Disposal in this reporting month
6.2 Summary of Daily Dredging Volume in this reporting month
7.1 Summary of environmental licensing and permit status
9.1 Upcoming EM&A Schedule
9.2 Construction Plan in the coming two month